Vice Chairman Ngo Tan Phuong urges construction progress of package No. 16, Ring Road 4 project
(BNP) – On the afternoon of March 14, Mr. Ngo Tan Phuong, Vice Chairman of the Provincial People's Committee inspected and urged the construction progress of Package No. 16, Ring Road 4 project - Hanoi Capital Region (section passing through Bac Ninh province).
Vice Chairman Ngo Tan Phuong (3rd from left) inspects the construction site of package 16, in Bac Ninh city.
Package No. 16 (located in in Bac Ninh city and Que Vo town) is 25.955 kilometers long, with Ring Road 4 being 11.745 kilometers and the connecting route measuring 14.210 kilometers. There are now 15 construction sites, including 12 road construction projects and 3 bridge construction sites.
Up to this point, the total construction volume of the package has reached 211,239/986,072 billion VND (21.42%) of the contract value, the payment value of completed volume is 81/211,239 billion VND (38.35%).
Directly inspecting the construction site of package No. 16 in Hap Linh and Nam Son wards (Bac Ninh city) and Yen Gia commune (Que Vo town), Vice Chairman Ngo Tan Phuong severely criticized the contractors, Hai Dang Construction Joint Stock Company and Construction Service and Trade Joint Stock Company 68, for delaying the progress; the contractor's capacity has not met the planned progress.
He urged that the Traffic and Agriculture Project Management Board direct and encourage contractors on the route to begin building as soon as possible on parts with available ground, as well as examine the work assignment plan in a systematic and scientific manner. The contractor must instantly establish documentation and working minutes; if progress is delayed three times, the job will be assigned to other construction units.