Illustrative photo.
The 110kV Outgoing Line Project after 220kV Lang Giang Transformer Station has a 110kV line passing through the communes of Tan Yen, Phuc Hoa, Nha Nam, Yen The, Tien Luc, Kep (Bac Ninh province). The land use area is about 24,780 m2.
The project has a scale of 03 outgoing lines. Of which, for feeder 1, construct 0.554 km of 4-circuit 110kV line and construct 5.948 km of 110kV double-circuit line from 220kV Lang Giang substation to connect to the 110kV Lang Giang - Cau Go line and the 110kV Tan Yen - Cau Go line (ACSR-300 conductor).
Feeder 2: Suspend 0.554 km of 2-circuit 110kV line and construct 5.674 km of 110kV double-circuit line to connect to the 110kV Lang Giang - Cau Go line (ACSR-300 conductor).
For feeder 3, construct 16.98 km of 4-circuit 110kV line (AC300 conductor); in which 02 110kV lines from 220kV Lang Giang substation are connected to the 110kV Doi Coc - Lang Giang line and 02 110kV lines from 220kV Lang Giang substation are connected to the 110kV Lang Giang - Huu Lung line. At the same time, 4.88 km of 110kV lines will be upgraded from 01 circuit to 05 circuits connecting to the 110kV Doi Coc - Lang Giang lines, 110kV Lang Giang - Huu Lung lines and 110kV Lang Giang - Cau Go lines (AC300 conductors and 2x240 AC conductors).
The total investment capital of the project is more than 378 billion VND. The operating period is 50 years, from the date the State allocates land or leases land to implement the project. Incentives and investment support are implemented in accordance with current laws.
Complete procedures for project preparation, land use plan registration, land recovery, compensation, site clearance support, land allocation, land lease, and land use conversion by the second quarter of 2026. Construction from the second quarter of 2026 to the first quarter of 2027. Complete project operation in the first quarter of 2027./.