Vice Chairman Ngo Tan Phuong inspects and urges progress of Package 16 of Ring Road 4 project

01/11/2024 14:48

(BNP) - On the morning of November 1, Mr. Ngo Tan Phuong, Vice Chairman of the Provincial People's Committee inspected and urged the progress of package No. 16 of the investment project to build Ring Road 4 - Hanoi Capital Region through Bac Ninh city and Que Vo town.


Vice Chairman of the Provincial People's Committee Ngo Tan Phuong (3rd from left) inspects the progress of package No. 16 through Bac Ninh city.

Package No. 16, the section through Bac Ninh city is over 14.2 km long; through Que Vo town is over 11.7 km long. On May 20, the Traffic Construction Project Management Board, the Department of Transport signed a contract with a consortium consisting of Nga Hai Company Limited, 68 Service and Trade Construction Joint Stock Company, Hai Dang Joint Stock Company and Bridge 75 Construction Joint Stock Company to build the project, which has a contract value of over VND 1,000 billion and an implementation time of 1,080 days.


Vice Chairman Ngo Tan Phuong (third from right) inspects and directs the removal of obstacles in the site clearance section through Nam Son ward, Bac Ninh city.

Currently, 12 road construction sites and 3 bridge construction sites are being implemented on the route with a total implementation volume of nearly VND 47 billion, reaching 4.36% of the contract value.


Vice Chairman Ngo Tan Phuong (3rd from left) inspects the site of package No. 16, section through Yen Gia commune, Que Vo town.

Directly inspecting the construction progress of package No. 16, Vice Chairman Ngo Tan Phuong emphasized that the investment project to build Ring Road 4 is a key project that the province pays special attention to. As a result, local authorities where the project passes through must thoroughly understand and strictly implement the province's directive documents on site clearance, as well as promptly complete the handover to the investor to ensure construction progress.

Households dismantle agricultural works and crops to hand over the site to the construction unit.

The Vice Chairman requested that the contractors strictly implement the implementation timeframe outlined in the plan. He asked the investor to make detailed plan, organize meetings with contractors to count the volume weekly and closely coordinate with the investor, the supervision consultant, and the local authorities to create consensus in the site clearance work...

By P.H