Vice Chairman Nguyen Huu Thanh inspects progress of key irrigation projects

02/05/2020 08:25

(BNP) - In the afternoon of April 27, Mr. Nguyen Huu Thanh, Member of Provincial Party Standing Committee, Vice Chairman of Provincial People's Committee inspected construction progress of Van Ninh Pumping Station (Gia Binh District) and Tri Phuong II Pumping Station (Tien Du District). These are 2 key projects in agriculture sector to celebrate 20th Provincial Party Congress, term 2020 - 2025.

Vice Chairman Nguyen Huu Thanh inspects progress of Van Ninh Pumping Station project.

Started in December 2019, Van Ninh pumping station consists of 4 machines with a total capacity of 3.11m3/s. Once it is completed, the pumping station will supply irrigation water for more than 6,000 hectares of agricultural land in Gia Binh district. Up to now, the project has been completed about 60% the construction work ans expects to be completed in September 2020.

Tri Phuong II Pumping Station consists of 3 main items including a level 1 Pumping station for both irrigation and drainage; a level 2 Pumping station; an irrigation and drainage canal system together with operation work. This is a modernly designed project that can directly take water from Duong River to supply water for nearly 7,000 ha of agricultural, industrial and urban land of Tien Du district and Tu Son town. After more than 1 year of implementation, the project has been completed over 70% of the construction work and expects to be completed in December 2020.

Directly inspecting the progress of 2 projects on-site, Vice Chairman Nguyen Huu Thanh asked the investor to mobilize maximum human resource, machinery and equipment for speeding up the construction progress as well as strictly supervising and ensuring project quality.