Trial operation of wastewater treatment plant in Phu Lam Industrial Cluster
(BNP) – After 18 months of construction, until now, the wastewater treatment plant in Phu Lam Industrial Cluster, Tien Du district (Plant) is put into operation of phase I with a treatment capacity of 6,000m3 per day and night.
The wastewater treatment plant in Phu Lam industrial cluster.
Starting construction in July 2022, the Plant is invested by Kinh Bac Green Environment Joint Stock Company with a total cost of more than VND 170 billion and its treatment capacity of 10,000m3 per day and night. In phase I, the wastewater treatment system with advanced technology was built, and entire technical infrastructure and other ancillary items were automatically operated; as well as the modern technological equipment system was invested with a treatment capacity of 6,000m3 per day and night. In Phase II, these above items continued to be constructed with a treatment capacity of 4,000m3 per day and night.
Currently, 08 enterprises in Phu Lam Industrial Cluster is connecting wastewater pipes to the Plant, among which, 04 enterprises have treated wastewater.
The Plant’s trial operation of phase I is important, contributing to the complete handling of wastewater pollution and gradual improvement of the environment in Phu Lam Industrial Cluster.